Grid infrastructure βΊ Connection queue βΊ Wind + storage
WIND + STORAGE Β· SPTWoodland Ridge
Woodland Ridge is a 150 MW wind + storage project in planning, connecting to the SP Transmission (south Scotland) network at Hawick 132kV Substation, with capacity due from July 2034. The connection agreement is held by Cubico UK Development Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Jul 2034 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-005110
- Customer
- Cubico UK Development Limited
- Technology
- Energy Storage System, Wind Onshore
- Total capacity
- 150 MW
- Change in this agreement
- +150 MW
- Capacity effective from
- 3 July 2034
- Connection site
- Hawick 132kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Hawick 132kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem