Grid infrastructure β€Ί Connection queue β€Ί Battery storage

BATTERY STORAGE Β· NGET

Norrington Gate

Norrington Gate is a 150 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Melksham B 132KV Substation, with capacity due from September 2037. The connection agreement is held by Adv 004 Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Sep 2037 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-002329
Customer
Adv 004 Limited
Technology
Energy Storage System
Total capacity
150 MW
Change in this agreement
+150 MW
Capacity effective from
15 September 2037
Connection site
Melksham B 132KV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Melksham B Β· Grid map

Other projects at Melksham B 132KV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem