Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SPT

Glennifer Road BESS

Glennifer Road BESS is a 150 MW battery storage project consented, connecting to the SP Transmission (south Scotland) network at Glennifer Road BESS 132kV substation, with capacity due from July 2028. The connection agreement is held by Drax BESS Neilston Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-003600
Customer
Drax BESS Neilston Limited
Technology
Energy Storage System
Total capacity
150 MW
Change in this agreement
+150 MW
Capacity effective from
31 July 2028
Connection site
Glennifer Road BESS 132kV substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The connection site could not be placed on the map.

Projects connecting near Glennifer Road BESS · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem