Grid infrastructure βΊ Connection queue βΊ Solar + storage
SOLAR + STORAGE Β· SHETKedrum Solar Farm
Kedrum Solar Farm is a 150 MW solar + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Blackhillock 275kV Substation, with capacity due from May 2030. The connection agreement is held by Rosside Energy Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom May 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003444
- Customer
- Rosside Energy Limited
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 150 MW
- Change in this agreement
- +150 MW
- Capacity effective from
- 30 May 2030
- Connection site
- Blackhillock 275kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Blackhillock 275kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem