Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown1,329586.0 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,329 projects · page 20 of 27
ProjectCapacityStageConnection siteFrom
Severn Road Avonmouth
Battery storage · Fpc Electric Land Limited
135 MWScoping Seabank GSP
National Grid (England & Wales)
Oct 2038
Builth Wells
Onshore wind · Aberedw Energy Park Limited
133 MWScoping Pont Abraham GSP
National Grid (England & Wales)
Oct 2026
UK057-B Whatton Estate
Solar + storage · Enif BESS Limited
130 MWScoping Ratcliffe GSP
National Grid (England & Wales)
Oct 2028
Saver & Pashley Farm Energy Park
Solar + storage · Elgin Energy Es Co Limited
130 MWScoping Ninfield GSP
National Grid (England & Wales)
Dec 2036
Sulgrave Solar PV
Solar · Edf Energy Renewables Limited
130 MWScoping East Claydon GSP (NGED EM)
National Grid (England & Wales)
Oct 2026
Denton Estate Solar PV and BESS
Solar + storage · Elgin Energy Es Co Limited
129 MWScoping Navenby 132kV Substation
National Grid (England & Wales)
Oct 2034
Vox Charlie
Battery storage · Vox Charlie Ltd
125 MWScoping Amersham Main 132kV Substation
National Grid (England & Wales)
Oct 2037
Llwynygog
Onshore wind · Esgair Galed Energy Park Limited
125 MWScoping Chirk GSP
National Grid (England & Wales)
Feb 2027
Axminster
Battery storage · HB825AXM LTD
120 MWAwaiting Consents Axminster 132kV Substation
National Grid (England & Wales)
Oct 2024
Axminster - New Connection
Battery storage · Enso Green Holdings B Limited
120 MWScoping Axminster 132kV Substation
National Grid (England & Wales)
Jun 2029
Brentford (SSEN-FBT624) -120MW BESS
Battery storage · Lightsource Renewable UK Development Limited
120 MWScoping West London Connection Node B 132kV substation
National Grid (England & Wales)
Oct 2038
Drakelow
Battery storage · Enso Green Holdings V Limited
120 MWScoping Drakelow 132kV Substation
National Grid (England & Wales)
Dec 2027
Iron Acton
Battery storage · HD000ACT LTD
120 MWConsents Approved Iron Acton 275kV Substation
National Grid (England & Wales)
Oct 2028
Iron Acton
Solar + storage · Iron Acton Green Limited
120 MWConsents Approved 132kV bay at Iron Acton Substation
National Grid (England & Wales)
Sep 2026
Kingsnorth
Solar + storage · Enso Green Holdings G Limited
120 MWScoping Kingsnorth 132kV Substation
National Grid (England & Wales)
Oct 2028
Lightsource Mon Solar 2
Solar + storage · Lightsource Spv 204 Limited
120 MWScoping Wylfa South 400kV Substation
National Grid (England & Wales)
Nov 2037
Lincomb Farm 120MW BESS Scheme
Battery storage · Fpc Electric Land Limited
120 MWScoping Bishops Wood 132kV Substation
National Grid (England & Wales)
Jun 2033
Middlewick Wind
Onshore wind · Dengie Marshes Wind Farm Limited
120 MWScoping Rayleigh Main GSP
National Grid (England & Wales)
Oct 2034
Pembroke (spare bay)
Battery storage · Pembroke Green Limited
120 MWConsents Approved Pembroke 132kV Substation
National Grid (England & Wales)
Jul 2028
Pigeon House BESS
Battery storage · Voltwise Power Holdings Limited
120 MWScoping Solent Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Ratcliffe on Soar BESS
Battery storage · Fpc Electric Land Limited
120 MWScoping Kegworth B (Derbyshire Connection Node C) 132kV Substation
National Grid (England & Wales)
Oct 2037
Uskmouth - New Connection
Battery storage · Aw1 Energy Storage Limited
120 MWUnder Construction/Commissioning Uskmouth 132kV Substation
National Grid (England & Wales)
Oct 2026
Vale of Neath (Rhigos Road)
Solar + storage · Elgin Energy Es Co Limited
120 MWScoping Hirwaun GSP
National Grid (England & Wales)
Dec 2036
West Burton
Solar + storage · Enso Green Holdings A Limited
120 MWUnder Construction/Commissioning West Burton 132kV Substation
National Grid (England & Wales)
Jun 2027
Wylfa Substation
Solar + storage · Wylfa Green Limited
120 MWScoping Wylfa 132kV Substation
National Grid (England & Wales)
Jun 2029
Brechfa Dau Wind Farm
Wind + storage · TRYDAN GWYRDD CYMRU (Welsh Government) Ltd
111 MWScoping Llandyfaelog 132kV Substation
National Grid (England & Wales)
Dec 2036
Barry Road Storage
Battery storage · Bsr Applications Limited
110 MWScoping Severn Connection Node A 132kV Substation
National Grid (England & Wales)
Oct 2037
Bodelwyddan BESS and PV
Solar + storage · Bodelwyddan Solar & Energy Storage Limited
110 MWScoping Bodelwyddan 400kV Substation
National Grid (England & Wales)
Oct 2029
Merthyr Solar and Battery
Solar · Eew Renewables Ltd
110 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
May 2029
Gwynt Alwen WF
Solar + storage · Bwlch Gwyn Wind Farm Limited
108 MWScoping North Wales connection Node A 400kV Substation
National Grid (England & Wales)
Jun 2030
Gwynt Alwen WF
Solar + storage · Bwlch Gwyn Wind Farm Limited
108 MWScoping North Wales connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2032
Twyn Hywel Cillfynydd
Onshore wind · Twyn Hywel Energy Park Ltd
108 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
Apr 2027
Bryn Tilti
Onshore wind · Rhiwlas Energy Park Limited
106 MWScoping Chirk GSP
National Grid (England & Wales)
Feb 2027
Old Stoke Rd BESS
Battery storage · Cubico UK Development Limited
105 MWScoping North Anglia Connection Node A 132kV Substation
National Grid (England & Wales)
Oct 2034
Alverdiscott
Battery storage · Pivoted Power LLP
100 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2036
Bradford West 100MW
Battery storage · Old Allen Road BESS Limited
100 MWConsents Approved Bradford West 275kV Substation
National Grid (England & Wales)
May 2027
Capenhurst 275KV Substation
Battery storage · Zenobe Capenhurst Limited
100 MWBuilt Capenhurst 275kV Substation
National Grid (England & Wales)
Didcot A GTs
Gas · RWE Generation UK Plc
100 MWBuilt Didcot 400kV Substation
National Grid (England & Wales)
Didcot Battery
Battery storage · Didcot Battery Limited
100 MWScoping Didcot 400/132Kv Substation
National Grid (England & Wales)
Mar 2027
Feckenham 100MW BESS
Battery storage · Energycog Ltd
100 MWScoping Warwickshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Frodsham Solar Park
Solar + storage · Frodsham Solar Limited
100 MWScoping Frodsham 132kV
National Grid (England & Wales)
Apr 2029
Fryston Lane 100MW BESS
Battery storage · GPC 2008 Ltd
100 MWScoping Leeds North Connection Node C 132kV Substation
National Grid (England & Wales)
Oct 2035
Galileo 08 Limited
Solar + storage · Galileo 08 Limited
100 MWScoping Mid Wales Connection Node A
National Grid (England & Wales)
Oct 2037
Hall Ings Farm Substation
Solar · O&G Group Limited
100 MWScoping Creyke Beck 132kV
National Grid (England & Wales)
Oct 2034
Larks Green Farm BESS
Battery storage · Voltalia UK Ltd
100 MWScoping Iron Acton 132kV Substation
National Grid (England & Wales)
Oct 2037
Llyn Lort II Energy Park
Onshore wind · Llyn Lort II Energy Park Limited
100 MWScoping Chirk 132kV
National Grid (England & Wales)
Nov 2037
Menter Mon Morlais Anglesey Marine Energy
Other · Menter Môn Morlais Limited
100 MWUnder Construction/Commissioning Penrhos GSP
National Grid (England & Wales)
Mar 2030
Mynydd Y Gwynt
Wind + storage · Edf Energy Renewables Limited
100 MWScoping Mid Wales Connection Node A 400Kv Substation
National Grid (England & Wales)
Oct 2037
Orchard BESS
Battery storage · RE Projects Development Limited
100 MWScoping Staffordshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Stretchford Farm Solar and Storage
Solar + storage · Bsr Applications Limited
100 MWScoping Abham 132kV Substation
National Grid (England & Wales)
Oct 2037
Page 20 of 27

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.