Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Lincomb Farm 120MW BESS Scheme

Lincomb Farm 120MW BESS Scheme is a 120 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at Bishops Wood 132kV Substation, with capacity due from June 2033. The connection agreement is held by Fpc Electric Land Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002442
Customer
Fpc Electric Land Limited
Technology
Energy Storage System
Total capacity
120 MW
Change in this agreement
+120 MW
Capacity effective from
30 June 2033
Connection site
Bishops Wood 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Bishops Wood · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem