Grid infrastructure βΊ Connection queue βΊ Solar
SOLAR Β· NGETSulgrave Solar PV
Sulgrave Solar PV is a 130 MW solar project in planning, connecting to the National Grid (England & Wales) network at East Claydon GSP (NGED EM), with capacity due from October 2026. The connection agreement is held by Edf Energy Renewables Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2026 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001572
- Customer
- Edf Energy Renewables Limited
- Technology
- PV Array (Photo Voltaic/solar)
- Total capacity
- 130 MW
- Change in this agreement
- +130 MW
- Capacity effective from
- 30 October 2026
- Connection site
- East Claydon GSP (NGED EM)
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Projects connecting near East Claydon GSP (NGED EM) Β· Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem