Iron Acton

Iron Acton is a 120 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at 132kV bay at Iron Acton Substation, with capacity due from September 2026. The connection agreement is held by Iron Acton Green Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000491-2
Customer
Iron Acton Green Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
120 MW
Change in this agreement
+21 MW
Capacity effective from
30 September 2026
Connection site
132kV bay at Iron Acton Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The connection site could not be placed on the map.

Projects connecting near · Grid map

Other projects at 132kV bay at Iron Acton Substation