BATTERY STORAGE · NGET

Ratcliffe on Soar BESS

Ratcliffe on Soar BESS is a 120 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at Kegworth B (Derbyshire Connection Node C) 132kV Substation, with capacity due from October 2037. The connection agreement is held by Fpc Electric Land Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002725
Customer
Fpc Electric Land Limited
Technology
Energy Storage System
Total capacity
120 MW
Change in this agreement
+120 MW
Capacity effective from
30 October 2037
Connection site
Kegworth B (Derbyshire Connection Node C) 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.

Projects connecting near Kegworth B (Derbyshire Connection Node C) · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem