Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23839.1 GW
Active in queue39.1 GW238 requests
Agreement signed10.6 GW60 requests
Withdrawn94580.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

238 requests ยท page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project G0678, Morrow County
Solar
1,200 MWIn study Morrow, ORWest Jun 2021target 2024
Solar project G0687, Sherman County
Solar
900 MWIn study Sherman, ORWest Aug 2021target 2024
Blue Bird Solar
Solar ยท Gigawatt Solar LLC
773 MWAgreement signed Johnson, TXERCOT Nov 2021target 2028
Solar project J2261, Jackson County
Solar
625 MWIn study Jackson, ARMISO Oct 2021target 2028
Solar project J2262, Jackson County
Solar
625 MWIn study Jackson, ARMISO Oct 2021target 2028
Solar project G0669, Crook County
Solar
600 MWIn study Crook, ORWest Feb 2021target 2027
Solar project G0673, Crook County
Solar
600 MWIn study Crook, ORWest Mar 2021target 2028
Solar project GEN-2021-030, Linn County
Solar
510 MWIn study Linn, KSSPP May 2021target 2026
Bayside Solar
Solar
509 MWPaused / redesign Victoria, TXERCOT Feb 2021target 2026
Solar project GEN-2021-096, Coffey County
Solar
500 MWIn study Coffey, KSSPP Apr 2021target 2027
Solar project J1855, Jackson County
Solar
500 MWIn study Jackson, ARMISO Nov 2021target 2026
Solar project G0712, Sherman County
Solar
448 MWIn study Sherman, ORWest Nov 2021target 2025
Solar project J1858, Mississippi County
Solar
440 MWIn study Mississippi, ARMISO Nov 2021target 2028
Poco Trail Solar
Solar ยท Eastern Trail Solar Center, LLC
439 MWIn study Wilbarger, TXERCOT Sep 2021target 2027
Grasshopper Solar
Solar ยท Grasshopper Solar LLC
408 MWIn study Haskell, TXERCOT Sep 2021target 2028
Compadre Solar
Solar ยท Hill Solar I, LLC
406 MWAgreement signed Hill, TXERCOT Mar 2021target 2025
Solar project J2268, Linn County
Solar
400 MWIn study Linn, IAMISO Aug 2021target 2024
Solar project J2098, Calhoun County
Solar
309 MWIn study Calhoun, MIMISO Aug 2021target 2026
Solar project GEN-2021-023, Grant County
Solar
306 MWAgreement signed Grant, KSSPP May 2021target 2030
Solar project GEN-2021-053, Muskogee County
Solar
300 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Solar project J2270, Sullivan County
Solar
300 MWIn study Sullivan, INMISO Aug 2021target 2024
Solar project 405, Rosebud County
Solar
300 MWPaused / redesign Rosebud, MTWest Feb 2021target 2024
Solar project G0711, Sherman County
Solar
300 MWIn study Sherman, ORWest Nov 2021target 2025
Blevins Solar
Solar ยท Blevins Solar, LLC
272 MWAgreement signed Falls, TXERCOT Feb 2021target 2026
OCI SunRoper
Solar ยท OCI SunRoper LLC
265 MWAgreement signed Wharton, TXERCOT Nov 2021target 2027
Miranda Solar Project
Solar ยท Miranda Solar Project, LLC
261 MWAgreement signed Mcmullen, TXERCOT Nov 2021target 2027
Sypert Branch Solar Project
Solar ยท Sypert Branch Solar LLC
261 MWAgreement signed Milam, TXERCOT Sep 2021target 2026
Roseland Solar II
Solar ยท Enel Green Power Roseland Solar, LLC
254 MWAgreement signed Falls, TXERCOT Oct 2021target 2025
Bayside II Solar
Solar
253 MWPaused / redesign Dewitt, TXERCOT Jul 2021target 2026
Tiger Solar
Solar ยท Vaca Del Sol, LLC
251 MWAgreement signed Jones, TXERCOT Apr 2021target 2027
Solar project IC-950, Mcduffie County
Solar
250 MWAgreement signed Mcduffie, GASoutheast Apr 2021target 2024
Solar project J2143, Chicot County
Solar
250 MWIn study Chicot, ARMISO Oct 2021target 2027
NY125A - Fort Covington Solar
Solar ยท Fort Covington Solar LLC
250 MWIn study Franklin, NYNYISO May 2021target 2028
Solar project IC-986, Lamar County
Solar
250 MWPaused / redesign Lamar, MSSoutheast Oct 2021target 2025
Solar project J1872, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Solar project GEN-2021-047, Mayes County
Solar
250 MWAgreement signed Mayes, OKSPP Apr 2021target 2029
Solar project J1873, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Solar project J2294, Mississippi County
Solar
250 MWIn study Mississippi, ARMISO Aug 2021target 2028
Solar project IC-972, Jasper County
Solar
250 MWPaused / redesign Jasper, GASoutheast Jul 2021target 2024
Solar project 171, Williamsburg County
Solar
249 MWUnder construction Williamsburg, SCSoutheast Oct 2021target 2028
Solar project J2149, Saline County
Solar
240 MWIn study Saline, ARMISO Nov 2021target 2024
DeSpain Solar Project
Solar ยท Gransolar Texas Thirteen LLC
236 MWIn study Kinney, TXERCOT Dec 2021target 2027
Solar project GEN-2021-018, Noble County
Solar
231 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Solar project J2317, Ouachita Parish County
Solar
225 MWIn study Ouachita Parish, LAMISO Dec 2021target 2027
Solar project GEN-2021-049, Lancaster County
Solar
225 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Utley Solar
Solar
222 MWPaused / redesign Freestone, TXERCOT Sep 2021target 2025
Goodalta Solar
Solar ยท GoodAlta Power Center LLC
221 MWIn study Navarro, TXERCOT Jan 2021target 2027
Solar project J2001, Newaygo County
Solar
220 MWIn study Newaygo, MIMISO Aug 2021target 2025
Grimes County Solar
Solar ยท Grimes County Solar Project, LLC
211 MWAgreement signed Grimes, TXERCOT Jan 2021target 2025
Two Rivers Solar
Solar ยท Two Rivers Solar, LLC
209 MWIn study Milam, TXERCOT Jul 2021target 2029
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)