🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

SOLAR · NYISO

NY125A - Fort Covington Solar

NY125A - Fort Covington Solar is a 250 MW solar request in interconnection study in the NYISO interconnection queue, in Franklin County, New York, connecting to NYPA.

Queue statusIn planning
  1. PlanningQueued May 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1183
Grid region
NYISO (New York)
Utility / transmission owner
NYPA
Developer
Fort Covington Solar LLC
Connection point (POI)
Moses-Willis 230 kV (MW1)
Location
Franklin County, New York
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
20 May 2021
Proposed online date
July 2028

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem