United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISONorth County Energy Storage
North County Energy Storage is a 20.0 MW battery storage request built and operating in the NYISO interconnection queue, in Franklin County, New York, connecting to NYPA.
Request details
- Queue ID
- 769
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- NY Power Authority
- Connection point (POI)
- Willis 115kV
- Location
- Franklin County, New York
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- SIS
- Queue status
- Operational
- Entered queue
- 5 October 2018
- Agreement signed
- 7 January 2021
- Came online
- September 2023
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- North Country WindOnshore wind · 380 MW · in study
- North Country Wind IIOnshore wind · 380 MW · in study
- NY125A - Fort Covington SolarSolar · 250 MW · in study
- NY125C - Little Salmon SolarSolar · 200 MW · in study
- NY Chateaugay 0 Willis Rd Storage (NYISO-C24-304-004)Battery storage · 150 MW · in study
- NY Chateaugay 0 Willis Rd StorageBattery storage · 150 MW · in study
- Jericho SolarSolar · 100 MW · in study
- Brookside SolarSolar · 100 MW · in study
- Chateaugay WindparkOnshore wind · 107 MW · built
- Jericho Rise WindOnshore wind · 77.7 MW · built
- Jericho Rise WindOnshore wind · 77.7 MW · built
- North County Energy StorageBattery storage · 20.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem