North County Energy Storage

North County Energy Storage is a 20.0 MW battery storage request built and operating in the NYISO interconnection queue, in Franklin County, New York, connecting to NYPA.

Queue statusOperating
  1. PlanningQueued Oct 2018 (completed)
  2. ConsentedJan 2021 (completed)
  3. Construction (completed)
  4. OperatingSep 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
769
Grid region
NYISO (New York)
Utility / transmission owner
NYPA
Developer
NY Power Authority
Connection point (POI)
Willis 115kV
Location
Franklin County, New York
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Study phase
SIS
Queue status
Operational
Entered queue
5 October 2018
Agreement signed
7 January 2021
Came online
September 2023

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.