United States › Grid › Interconnection queues › New York
ONSHORE WIND · NYISOJericho Rise Wind
Jericho Rise Wind is a 77.7 MW onshore wind request built and operating in the NYISO interconnection queue, in Franklin County, New York, connecting to NYPA.
Request details
- Queue ID
- 397
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Jericho Rise Wind Farm, LLC
- Connection point (POI)
- Willis Substation 115kV
- Location
- Franklin County, New York
- Technology
- Wind: 77.7 MW
- Total requested
- 77.7 MW
- Study phase
- SRIS, FS
- Queue status
- Operational
- Entered queue
- 21 December 2012
- Came online
- February 2017
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- North Country WindOnshore wind · 380 MW · in study
- North Country Wind IIOnshore wind · 380 MW · in study
- NY125A - Fort Covington SolarSolar · 250 MW · in study
- NY125C - Little Salmon SolarSolar · 200 MW · in study
- NY Chateaugay 0 Willis Rd Storage (NYISO-C24-304-004)Battery storage · 150 MW · in study
- NY Chateaugay 0 Willis Rd StorageBattery storage · 150 MW · in study
- Jericho SolarSolar · 100 MW · in study
- Brookside SolarSolar · 100 MW · in study
- Chateaugay WindparkOnshore wind · 107 MW · built
- Jericho Rise WindOnshore wind · 77.7 MW · built
- North County Energy StorageBattery storage · 20.0 MW · built
- North County Energy StorageBattery storage · 20.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem