Solar project IC-972, Jasper County

Solar project IC-972, Jasper County is a 250 MW solar request suspended in the Southeast interconnection queue, in Jasper County, Georgia, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued Jul 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-972
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Eatonton Primary - Porterdale Primary 230 kV Line
Location
Jasper County, Georgia
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Queue status
Suspended
Entered queue
14 July 2021
Proposed online date
August 2024

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.