SOLAR · MISOSolar project J2143, Chicot County
Solar project J2143, Chicot County is a 250 MW solar request in interconnection study in the MISO interconnection queue, in Chicot County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusIn planning
- PlanningQueued Oct 2021 (current stage)
- ConsentedNov 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2143
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- Lake Village Bagby 115 KV
- Location
- Chicot County, Arkansas
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 October 2021
- Agreement signed
- 19 November 2025
- Proposed online date
- March 2027
Location
Marker shows the centre of Chicot County; the queue data does not give exact sites.
Other requests in Chicot County
- Solar project J2985, Chicot CountySolar · 135 MW · in study
- Solar project J620, Chicot CountySolar · 100 MW · built
- Solar project J3426, Chicot CountySolar · 500 MW · withdrawn
- Solar project J2850, Chicot CountySolar · 250 MW · withdrawn
- Solar project J2451, Chicot CountySolar · 200 MW · withdrawn
- Solar project J698, Chicot CountySolar · 150 MW · withdrawn
- Solar project J922, Chicot CountySolar · 100 MW · withdrawn
- Solar project J2941, Chicot CountySolar · 100 MW · withdrawn
- Solar project J2644, Chicot CountySolar · 90.0 MW · withdrawn
- Battery storage project J2995, Chicot CountyBattery storage · 80.0 MW · withdrawn
- Solar project J350, Chicot CountySolar · 50.0 MW · withdrawn