SOLAR Β· MISOSolar project J350, Chicot County
Solar project J350, Chicot County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Chicot County, Arkansas.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2014 (completed)
- Withdrawn / abandonedJun 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J350
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Lake Village Bagby 115 kV Substation
- Location
- Chicot County, Arkansas
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 19 May 2014
- Withdrawn
- June 2015
Location
Marker shows the centre of Chicot County; the queue data does not give exact sites.
Other requests in Chicot County
- Solar project J2143, Chicot CountySolar Β· 250 MW Β· in study
- Solar project J2985, Chicot CountySolar Β· 135 MW Β· in study
- Solar project J620, Chicot CountySolar Β· 100 MW Β· built
- Solar project J3426, Chicot CountySolar Β· 500 MW Β· withdrawn
- Solar project J2850, Chicot CountySolar Β· 250 MW Β· withdrawn
- Solar project J2451, Chicot CountySolar Β· 200 MW Β· withdrawn
- Solar project J698, Chicot CountySolar Β· 150 MW Β· withdrawn
- Solar project J922, Chicot CountySolar Β· 100 MW Β· withdrawn
- Solar project J2941, Chicot CountySolar Β· 100 MW Β· withdrawn
- Solar project J2644, Chicot CountySolar Β· 90.0 MW Β· withdrawn
- Battery storage project J2995, Chicot CountyBattery storage Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem