United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J1872, Union County
Solar project J1872, Union County is a 250 MW solar request in interconnection study in the MISO interconnection queue, in Union County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusIn planning
- PlanningQueued Aug 2021 (current stage)
- ConsentedOct 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1872
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- El Dorado 500kV Substation
- Location
- Union County, Arkansas
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 16 August 2021
- Agreement signed
- 29 October 2025
- Proposed online date
- November 2028
Location
Marker shows the centre of Union County; the queue data does not give exact sites.
Other requests in Union County
- Gas project J3874, Union CountyGas · 770 MW · in study
- Solar project J3889, Union CountySolar · 350 MW · in study
- Solar project J1873, Union CountySolar · 250 MW · in study
- Solar project J3888, Union CountySolar · 150 MW · in study
- Solar project J1612, Union CountySolar · 100 MW · in study
- Gas project J376, Union CountyGas · 1,270 MW · built
- Gas project J433, Union CountyGas · 1,270 MW · withdrawn
- Solar project J3484, Union CountySolar · 200 MW · withdrawn
- Solar project J3038, Union CountySolar · 150 MW · withdrawn
- Solar project J3037, Union CountySolar · 150 MW · withdrawn
- Battery storage project J2468, Union CountyBattery storage · 130 MW · withdrawn
- Solar project J1443, Union CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem