United States › Grid › Interconnection queues › Arkansas
GAS · MISOGas project J376, Union County
Gas project J376, Union County is a 1,270 MW gas request built and operating in the MISO interconnection queue, in Union County, Arkansas.
Request details
- Queue ID
- J376
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- El Dorado substation
- Location
- Union County, Arkansas
- Technology
- Gas: 1,270 MW
- Total requested
- 1,270 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 7 July 2014
- Agreement signed
- 27 May 2015
- Proposed online date
- December 2016
- Came online
- December 2016
Location
Marker shows the centre of Union County; the queue data does not give exact sites.
Other requests in Union County
- Gas project J3874, Union CountyGas · 770 MW · in study
- Solar project J3889, Union CountySolar · 350 MW · in study
- Solar project J1872, Union CountySolar · 250 MW · in study
- Solar project J1873, Union CountySolar · 250 MW · in study
- Solar project J3888, Union CountySolar · 150 MW · in study
- Solar project J1612, Union CountySolar · 100 MW · in study
- Gas project J433, Union CountyGas · 1,270 MW · withdrawn
- Solar project J3484, Union CountySolar · 200 MW · withdrawn
- Solar project J3038, Union CountySolar · 150 MW · withdrawn
- Solar project J3037, Union CountySolar · 150 MW · withdrawn
- Battery storage project J2468, Union CountyBattery storage · 130 MW · withdrawn
- Solar project J1443, Union CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem