🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Miranda Solar Project

Miranda Solar Project is a 261 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Mcmullen County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2021 (completed)
  2. ConsentedJul 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0161
Grid region
ERCOT (Texas)
Developer
Miranda Solar Project, LLC
Connection point (POI)
Tap 345kV 5709 Fowlerton - 5901 San Miguel Ckt 1
Location
Mcmullen County, Texas
Technology
Solar: 261 MW
Total requested
261 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
3 November 2021
Agreement signed
16 July 2024
Proposed online date
December 2027

Location

Marker shows the centre of Mcmullen County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem