United States โบ Grid โบ Interconnection queues โบ Washington
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Washington (2022 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Other project G0730, Garfield County Other |
1,125 MW | Withdrawn / abandoned |
| Onshore wind project G0815, Grays Harbor County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Wind + storage project G0735, Grays Harbor County Wind + storage |
1,000 MW | Withdrawn / abandoned |
| Onshore wind project G0814, Grays Harbor County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Onshore wind project G0816, Grays Harbor County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project G0736, Asotin County Solar + storage |
600 MW | Withdrawn / abandoned |
| Battery storage project C2-24, Grant County Battery storage ยท PacifiCorp |
500 MW | Withdrawn / abandoned |
| Solar + storage project G0824, Garfield County Solar + storage |
455 MW | Withdrawn / abandoned |
| Solar + storage project G0729, Douglas County Solar + storage |
450 MW | Withdrawn / abandoned |
| Solar + storage project G0741, Klickitat County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project G0743, Benton County Solar |
315 MW | Withdrawn / abandoned |
| Battery storage project G0766, Benton County Battery storage |
315 MW | Withdrawn / abandoned |
| Battery storage project G0799, Benton County Battery storage |
315 MW | Withdrawn / abandoned |
| Onshore wind project G0727, Garfield County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project C2-51, Clark County Battery storage ยท PacifiCorp |
300 MW | Withdrawn / abandoned |
| Solar + storage project 133, Garfield County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project G0742, Grant County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project C2-50, Skamania County Battery storage ยท PacifiCorp |
300 MW | Withdrawn / abandoned |
| Solar + storage project C2-174, Benton County Solar + storage |
270 MW | Withdrawn / abandoned |
| Solar project G0833, Adams County Solar |
204 MW | Withdrawn / abandoned |
| Solar project 4, Douglas County Solar |
200 MW | Withdrawn / abandoned |
| Solar project G0767, Grant County Solar |
200 MW | Withdrawn / abandoned |
| Solar project G0740, Grant County Solar |
200 MW | Withdrawn / abandoned |
| Solar + storage project C2-141, Walla Walla County Solar + storage ยท ACE DevCo NC, LLC |
199 MW | Withdrawn / abandoned |
| Wind + storage project C2-80, Yakima County Wind + storage |
199 MW | Withdrawn / abandoned |
| Onshore wind project 131, Garfield County Onshore wind |
198 MW | Withdrawn / abandoned |
| Onshore wind project G0769, Lewis County Onshore wind |
170 MW | Withdrawn / abandoned |
| Solar + storage project C2-41, Asotin County Solar + storage |
160 MW | Withdrawn / abandoned |
| Solar + storage project 22-107, Garfield County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar project 137, Columbia County Solar |
150 MW | Withdrawn / abandoned |
| Solar + storage project G0746, Benton County Solar + storage |
150 MW | Withdrawn / abandoned |
| Battery storage project C2-157, Walla Walla County Battery storage |
150 MW | Withdrawn / abandoned |
| Battery storage project 136, King County Battery storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project 130, Garfield County Onshore wind |
140 MW | Withdrawn / abandoned |
| Battery storage project 132, Thurston County Battery storage |
127 MW | Withdrawn / abandoned |
| Solar + storage project C2-127, Yakima County Solar + storage |
100 MW | Withdrawn / abandoned |
| Battery storage project 134, Thurston County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C2-128, Yakima County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C2-33, Yakima County Solar + storage |
94.0 MW | Withdrawn / abandoned |
| Solar + storage project C2-35, Yakima County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Battery storage project C2-192, Yakima County Battery storage |
40.0 MW | Withdrawn / abandoned |
| Battery storage project C2-193, Yakima County Battery storage |
40.0 MW | Withdrawn / abandoned |
| Solar + storage project C2-195, Yakima County Solar + storage |
40.0 MW | Withdrawn / abandoned |
| Battery storage project C2-196, Yakima County Battery storage |
40.0 MW | Withdrawn / abandoned |
| Battery storage project C2-194, Yakima County Battery storage |
40.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)