πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

SOLAR Β· WEST

Solar project G0743, Benton County

Solar project G0743, Benton County is a 315 MW solar request withdrawn in the West interconnection queue, in Benton County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0743
Grid region
West (non-ISO utilities)
Connection point (POI)
Wine Country-Midway #1
Location
Benton County, Washington
Technology
Solar: 315 MW
Total requested
315 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
24 May 2022
Proposed online date
June 2026

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem