πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project G0769, Lewis County

Onshore wind project G0769, Lewis County is a 170 MW onshore wind request withdrawn in the West interconnection queue, in Lewis County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0769
Grid region
West (non-ISO utilities)
Connection point (POI)
Longview-Chehalis No 1 and No 3 230 kV line.
Location
Lewis County, Washington
Technology
Wind: 170 MW
Total requested
170 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
11 August 2022
Proposed online date
October 2026

Location

Marker shows the centre of Lewis County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Lewis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem