United States βΊ Grid βΊ Interconnection queues βΊ Washington
BATTERY STORAGE Β· WESTBattery storage project 125, Lewis County
Battery storage project 125, Lewis County is a 170 MW battery storage request withdrawn in the West interconnection queue, in Lewis County, Washington, connecting to Puget Sound Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 125
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Puget Sound Energy
- Connection point (POI)
- Tono 115 kV Substation
- Location
- Lewis County, Washington
- Technology
- Battery: 170 MW
- Total requested
- 170 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 31 August 2021
- Proposed online date
- April 2026
Location
Marker shows the centre of Lewis County; the queue data does not give exact sites.
Power plants in Washington Β· Transmission lines in Washington
Other requests in Lewis County
- Other project G1072, Lewis CountyOther Β· 667 MW Β· in study
- Wind + storage project G1007, Lewis CountyWind + storage Β· 600 MW Β· in study
- Gas project 113, Lewis CountyGas Β· 219 MW Β· suspended
- Centralia Generation AdditionGas Β· 248 MW Β· built
- Onshore wind project 46, Lewis CountyOnshore wind Β· 137 MW Β· built
- Centralia GenerationGas Β· 50.0 MW Β· built
- 1100MW PaulGas Β· 1,100 MW Β· withdrawn
- Onshore wind project G0595, Lewis CountyOnshore wind Β· 307 MW Β· withdrawn
- Battery storage project 106, Lewis CountyBattery storage Β· 200 MW Β· withdrawn
- Onshore wind project G0718, Lewis CountyOnshore wind Β· 170 MW Β· withdrawn
- Onshore wind project G0769, Lewis CountyOnshore wind Β· 170 MW Β· withdrawn
- Onshore wind project G0515, Lewis CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem