ONSHORE WIND Β· WEST

Onshore wind project G0595, Lewis County

Onshore wind project G0595, Lewis County is a 307 MW onshore wind request withdrawn in the West interconnection queue, in Lewis County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0595
Grid region
West (non-ISO utilities)
Connection point (POI)
BPA's Satsop 230 kV Substation
Location
Lewis County, Washington
Technology
Wind: 307 MW
Total requested
307 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
20 July 2018
Proposed online date
December 2022

Location

Marker shows the centre of Lewis County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Lewis County