United States › Grid › Interconnection queues › Washington

WIND + STORAGE · WEST

Wind + storage project G1007, Lewis County

Wind + storage project G1007, Lewis County is a 600 MW wind + storage request in interconnection study in the West interconnection queue, in Lewis County, Washington.

Queue statusIn planning
  1. PlanningQueued Nov 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G1007
Grid region
West (non-ISO utilities)
Connection point (POI)
Paul Substation
Location
Lewis County, Washington
Technology
Wind: 300 MW · Battery: 300 MW
Total requested
600 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
17 November 2023
Proposed online date
October 2030

Location

Marker shows the centre of Lewis County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Lewis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem