πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project 130, Garfield County

Onshore wind project 130, Garfield County is a 140 MW onshore wind request withdrawn in the West interconnection queue, in Garfield County, Washington, connecting to Puget Sound Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
130
Grid region
West (non-ISO utilities)
Utility / transmission owner
Puget Sound Energy
Connection point (POI)
Dodge Junction 230 kV Substation
Location
Garfield County, Washington
Technology
Wind: 140 MW
Total requested
140 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
3 February 2022
Proposed online date
September 2025

Location

Marker shows the centre of Garfield County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Garfield County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem