πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Texas (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown357,717 MW
Active in queue14.0 GW75 requests
Agreement signed7,717 MW35 requests
Withdrawn10519.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

35 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Renegade Project
Solar Β· Renegade Renewable LLC
516 MWAgreement signed Deaf Smith, TXERCOT Feb 2019target 2027
Buffalo Creek
Solar Β· Lincoln Clean Energy Development
439 MWAgreement signed Fort Bend, TXERCOT Aug 2019target 2026
Space City Solar
Solar Β· Apollo Solar Ranch, LLC
366 MWAgreement signed Wharton, TXERCOT Nov 2019target 2027
Fighting Jays Solar
Solar Β· AP Solar Holdings, LLC
351 MWAgreement signed Fort Bend, TXERCOT Mar 2019target 2026
Greyhound Solar
Solar Β· Rockhound Solar 2, LLC dba "Greyhound Solar"
336 MWAgreement signed Ector, TXERCOT Mar 2019target 2026
Pecan Prairie North
Solar Β· CG Leon County II LLC
321 MWAgreement signed Leon, TXERCOT Sep 2019target 2027
Hickerson Solar
Solar + storage Β· Hickerson Solar
311 MWAgreement signed Bosque, TXERCOT May 2019target 2025
Sisters Solar
Solar + storage Β· Oberon Solar LLC
302 MWAgreement signed Ector, TXERCOT Feb 2019target 2027
Board Creek Wind
Onshore wind Β· Limestone Wind Project, LLC
299 MWAgreement signed Navarro, TXERCOT Apr 2019target 2026
Monarch Creek Wind
Onshore wind Β· MONARCH CREEK WIND, LLC
284 MWAgreement signed Throckmorton, TXERCOT Apr 2019target 2027
Sbranch Solar
Solar Β· Bernard Creek Solar, LLC
234 MWAgreement signed Wharton, TXERCOT Jan 2019target 2026
Oystercatcher Solar
Solar Β· Oystercatcher Solar, LLC
222 MWAgreement signed Ellis, TXERCOT May 2019target 2026
Crowded Star Solar
Solar + storage Β· Jones City Solar, LLC
219 MWAgreement signed Jones, TXERCOT Jan 2019target 2026
New Hickory Solar
Solar Β· New Hickory Solar LLC
209 MWAgreement signed Jackson, TXERCOT Jan 2019target 2026
Battery storage project GEN-2019-011, Yoakum County
Battery storage
207 MWAgreement signed Yoakum, TXSPP Apr 2019target 2028
Rockefeller Storage
Battery storage Β· Mittel Rockefeller Storage LLC
207 MWAgreement signed Schleicher, TXERCOT Oct 2019target 2027
Shaula II Solar
Solar + storage Β· Shaula Energy Project II, LLC
205 MWAgreement signed Dewitt, TXERCOT Dec 2019target 2026
Shaula I Solar
Solar + storage Β· Shaula Energy Project, LLC
205 MWAgreement signed Dewitt, TXERCOT Dec 2019target 2026
Corazon Solar Phase II
Solar + storage Β· BAYWA R.E. SOLAR PROJECTS
204 MWAgreement signed Webb, TXERCOT Dec 2019target 2028
Big Star Solar
Solar Β· RWE Solar Development, LLC
203 MWAgreement signed Bastrop, TXERCOT Aug 2019target 2026
Felix North Solar
Solar + storage Β· Crescent Solar, LLC
201 MWAgreement signed Wilbarger, TXERCOT Jan 2019target 2028
Millers Branch Solar I
Solar Β· Miller's Branch Solar, LLC
200 MWAgreement signed Haskell, TXERCOT Dec 2019target 2025
Armadillo Solar
Solar Β· Armadillo Solar Center, LLC
200 MWAgreement signed Navarro, TXERCOT Aug 2019target 2026
Tres Bahias Solar
Solar Β· Tres Bahias Solar Power LLC
195 MWAgreement signed Calhoun, TXERCOT Mar 2019target 2025
Nightfall Solar
Solar Β· BDPU SOLAR NIGHTFALL, LLC
181 MWAgreement signed Uvalde, TXERCOT May 2019target 2026
Water Valley Wind Energy
Onshore wind Β· Water Valley Wind Energy, LLC
180 MWAgreement signed Tom Green, TXERCOT Jan 2019target 2027
Eliza Solar
Solar Β· Ables Springs Solar, LLC
152 MWAgreement signed Kaufman, TXERCOT Jun 2019target 2025
Ulysses Solar
Solar Β· BNB Tennyson Solar LLC
151 MWAgreement signed Coke, TXERCOT Jan 2019target 2027
Grandslam Solar
Solar Β· Grandslam Solar, L.L.C.
122 MWAgreement signed Atascosa, TXERCOT Jul 2019target 2026
Dove Run Solar
Solar Β· Dove Run Solar Project, LLC
121 MWAgreement signed Duval, TXERCOT May 2019target 2027
Lamkin Solar
Solar Β· Commanche Solar, LLC
102 MWAgreement signed Comanche, TXERCOT Jun 2019target 2027
Long Point Storage
Solar + storage Β· Long Point Storage, LLC
101 MWAgreement signed Brazoria, TXERCOT Nov 2019target 2026
DAMAZO (Second Division) SOLAR
Solar Β· TX Gulf Solar 1 LLC
100 MWAgreement signed Brazoria, TXERCOT Mar 2019target 2025
Ryan Energy Storage
Battery storage Β· Ryan Storage LLC
51.6 MWAgreement signed Coryell, TXERCOT Jan 2019target 2026
Wise County Power Repower (CT1, CT2)
Gas Β· Wise County Power Company LLC
21.0 MWAgreement signed Wise, TXERCOT Jul 2019target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)