United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTUlysses Solar
Ulysses Solar is a 151 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Coke County, Texas.
Queue statusConsented
- PlanningQueued Jan 2019 (completed)
- ConsentedOct 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 21INR0253
- Grid region
- ERCOT (Texas)
- Developer
- BNB Tennyson Solar LLC
- Connection point (POI)
- 60072 Odysseus Substation 345 kV
- Location
- Coke County, Texas
- Technology
- Solar: 151 MW
- Total requested
- 151 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 25 January 2019
- Agreement signed
- 3 October 2022
- Proposed online date
- March 2027
Location
Marker shows the centre of Coke County; the queue data does not give exact sites.
Other requests in Coke County
- Roboman SolarSolar · 273 MW · in study
- Coke BESSBattery storage · 220 MW · in study
- Rocky Point BESSBattery storage · 151 MW · in study
- Hayrick BESSBattery storage · 114 MW · in study
- Fort Chadbourne Cattle BESSBattery storage · 50.2 MW · in study
- Aviator WindOnshore wind · 525 MW · built
- BlueBell SolarSolar · 30.0 MW · built
- Meissa SolarSolar · 136 MW · withdrawn
- Olive SolarSolar · 39.6 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem