United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTBlueBell Solar
BlueBell Solar is a 30.0 MW solar request built and operating in the ERCOT interconnection queue, in Coke County, Texas.
Request details
- Queue ID
- 16INR0019
- Grid region
- ERCOT (Texas)
- Developer
- Nextera
- Connection point (POI)
- 76090 Divide 345kV
- Location
- Coke County, Texas
- Technology
- Solar: 30.0 MW
- Total requested
- 30.0 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 14 November 2013
- Agreement signed
- 19 August 2015
- Proposed online date
- December 2019
- Came online
- November 2019
Location
Marker shows the centre of Coke County; the queue data does not give exact sites.
Other requests in Coke County
- Ulysses SolarSolar Β· 151 MW Β· agreement signed
- Roboman SolarSolar Β· 273 MW Β· in study
- Coke BESSBattery storage Β· 220 MW Β· in study
- Rocky Point BESSBattery storage Β· 151 MW Β· in study
- Hayrick BESSBattery storage Β· 114 MW Β· in study
- Fort Chadbourne Cattle BESSBattery storage Β· 50.2 MW Β· in study
- Aviator WindOnshore wind Β· 525 MW Β· built
- Meissa SolarSolar Β· 136 MW Β· withdrawn
- Olive SolarSolar Β· 39.6 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem