BATTERY STORAGE · ERCOT

Hayrick BESS

Hayrick BESS is a 114 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Coke County, Texas.

Queue statusIn planning
  1. PlanningQueued Aug 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0135
Grid region
ERCOT (Texas)
Developer
Gransolar Texas Five LLC
Connection point (POI)
6351 Nicole 138kV
Location
Coke County, Texas
Technology
Battery: 114 MW
Total requested
114 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
16 August 2022
Proposed online date
March 2028

Location

Marker shows the centre of Coke County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Coke County