United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Meissa Solar

Meissa Solar is a 136 MW solar request withdrawn in the ERCOT interconnection queue, in Coke County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedJun 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0311
Grid region
ERCOT (Texas)
Developer
BLUE STONE RENEWABLE VIII LLC
Connection point (POI)
60417 Tennyson 138kV
Location
Coke County, Texas
Technology
Solar: 136 MW
Total requested
136 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
23 April 2019
Proposed online date
March 2022
Withdrawn
June 2021

Location

Marker shows the centre of Coke County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Coke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem