🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Long Point Storage

Long Point Storage is a 101 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2019 (completed)
  2. ConsentedAug 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0444
Grid region
ERCOT (Texas)
Developer
Long Point Storage, LLC
Connection point (POI)
138 KV (CEHE Sub) Tap Burke (42410) - Eagle Nest (42430) ckt 02
Location
Brazoria County, Texas
Technology
Battery: 101 MW · Battery
Total requested
101 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
1 November 2019
Agreement signed
28 August 2023
Proposed online date
December 2026

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem