OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Missouri

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25251.8 GW
Active in queue29.7 GW124 requests
Agreement signed7,888 MW34 requests
Withdrawn25251.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

252 requests ยท page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Nuclear project G733, Callaway County
Nuclear
1,650 MWWithdrawn / abandoned Callaway, MOMISO Feb 2007target 2009
Coal project GEN-2001-007, Platte County
Coal
900 MWWithdrawn / abandoned Platte, MOSPP Feb 2001target 2005
Coal project GEN-2004-012, Platte County
Coal
900 MWWithdrawn / abandoned Platte, MOSPP Apr 2004target 2009
Onshore wind project J957, Mercer County
Onshore wind
800 MWWithdrawn / abandoned Mercer, MOMISO Mar 2018target 2010
Coal project GEN-2001-006, Platte County
Coal
700 MWWithdrawn / abandoned Platte, MOSPP Feb 2001
Solar + storage project GEN-2022-209, Andrew County
Solar + storage
600 MWWithdrawn / abandoned Andrew, MOSPP Mar 2023target 2027
Gas project GEN-2003-011, Jasper County
Gas
600 MWWithdrawn / abandoned Jasper, MOSPP Jul 2003target 2010
Gas project GEN-2001-031, Cooper County
Gas
596 MWWithdrawn / abandoned Cooper, MOSPP Sep 2001
Gas project GEN-2000-008, Jackson County
Gas
560 MWWithdrawn / abandoned Jackson, MOSPP
Coal project GEN-2003-007, Jasper County
Coal
550 MWWithdrawn / abandoned Jasper, MOSPP Jul 2003target 2009
Coal project GEN-2003-014, Lawrence County
Coal
550 MWWithdrawn / abandoned Lawrence, MOSPP Jul 2003target 2009
Gas project GEN-2001-029, Cooper County
Gas
540 MWWithdrawn / abandoned Cooper, MOSPP Aug 2001
Gas project GEN-2001-032, Cooper County
Gas
528 MWWithdrawn / abandoned Cooper, MOSPP Sep 2001
Onshore wind project GI-113, Randolph County
Onshore wind
500 MWWithdrawn / abandoned Randolph, MOSoutheast Jan 2023target 2026
Other project J1489, Ralls County
Other
500 MWWithdrawn / abandoned Ralls, MOMISO Apr 2019target 2024
Solar + storage project J3106, Pemiscot County
Solar + storage
500 MWWithdrawn / abandoned Pemiscot, MOMISO Sep 2022target 2025
Onshore wind project J115, St. Francois County
Onshore wind
500 MWWithdrawn / abandoned St. Francois, MOMISO Feb 2010target 2012
Onshore wind project GI-114, Randolph County
Onshore wind
500 MWWithdrawn / abandoned Randolph, MOSoutheast Jan 2023target 2026
Solar + storage project J3102, Pemiscot County
Solar + storage
500 MWWithdrawn / abandoned Pemiscot, MOMISO Sep 2022target 2025
Gas project GI-99, Butler County
Gas
470 MWWithdrawn / abandoned Butler, MOSoutheast Jul 2022target 2026
Gas project GEN-2024-053, Nodaway County
Gas
451 MWWithdrawn / abandoned Nodaway, MOSPP Oct 2024target 2032
Gas project GEN-2024-028, Nodaway County
Gas
451 MWWithdrawn / abandoned Nodaway, MOSPP Oct 2024target 2030
Solar project GI-85, Dade County
Solar
436 MWWithdrawn / abandoned Dade, MOSoutheast Sep 2019target 2027
Onshore wind project J682, Schuyler County
Onshore wind
400 MWWithdrawn / abandoned Schuyler, MOMISO Jul 2016target 2019
Onshore wind project J966, Putnam County
Onshore wind
400 MWWithdrawn / abandoned Putnam, MOMISO Mar 2018target 2020
Onshore wind project GEN-2022-208, Andrew County
Onshore wind
400 MWWithdrawn / abandoned Andrew, MOSPP Mar 2023target 2027
Onshore wind project J1082, Grundy County
Onshore wind
400 MWWithdrawn / abandoned Grundy, MOMISO Mar 2018target 2020
Onshore wind project GEN-2018-041, Ralls County
Onshore wind
400 MWWithdrawn / abandoned Ralls, MOSPP May 20182025
Solar project GEN-2022-168, Henry County
Solar
380 MWWithdrawn / abandoned Henry, MOSPP Feb 2023target 2027
Solar project GI-97, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Solar project GI-106, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Gas project GEN-2007-018, Pettis County
Gas
315 MWWithdrawn / abandoned Pettis, MOSPP Apr 2007target 2010
Solar project J3404, Macon County
Solar
300 MWWithdrawn / abandoned Macon, MOMISO Apr 2024target 2028
Solar project GI-74, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Solar project GI-72, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Nov 2018target 2021
Solar project GI-76, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Solar project GI-73, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Onshore wind project GI-50, Atchison County
Onshore wind
300 MWWithdrawn / abandoned Atchison, MOSoutheast Dec 2014target 2016
Solar project J2043, Callaway County
Solar
300 MWWithdrawn / abandoned Callaway, MOMISO Apr 2022target 2025
Onshore wind project GEN-2006-017, Nodaway County
Onshore wind
300 MWWithdrawn / abandoned Nodaway, MOSPP Jun 2006target 2008
Onshore wind project GEN-2009-012, Holt County
Onshore wind
300 MWWithdrawn / abandoned Holt, MOSPP Mar 2009target 2012
Solar project GEN-2018-022, Nodaway County
Solar
300 MWWithdrawn / abandoned Nodaway, MOSPP May 20182025
Solar project GI-75, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Battery storage project J3690, Scott County
Battery storage
300 MWWithdrawn / abandoned Scott, MOMISO Apr 2024target 2028
Solar project J3958, Sullivan County
Solar
300 MWWithdrawn / abandoned Sullivan, MOMISO Apr 2025target 2029
Solar project GI-70, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Onshore wind project J1177, Schuyler County
Onshore wind
300 MWWithdrawn / abandoned Schuyler, MOMISO Mar 2018target 2020
Solar project J3307, Callaway County
Solar
300 MWWithdrawn / abandoned Callaway, MOMISO Apr 2024target 2027
Onshore wind project GEN-2009-029, Holt County
Onshore wind
300 MWWithdrawn / abandoned Holt, MOSPP Jul 2009target 2012
Solar project GEN-2023-115, Cooper County
Solar
300 MWWithdrawn / abandoned Cooper, MOSPP Oct 2023target 2030
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)