πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

ONSHORE WIND Β· MISO

Onshore wind project J682, Schuyler County

Onshore wind project J682, Schuyler County is a 400 MW onshore wind request withdrawn in the MISO interconnection queue, in Schuyler County, Missouri.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J682
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Schuyler County, Missouri
Technology
Wind: 400 MW
Total requested
400 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
11 July 2016
Proposed online date
September 2019
Withdrawn
June 2017

Location

Marker shows the centre of Schuyler County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Schuyler County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem