United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR Β· SPP

Solar project GEN-2022-168, Henry County

Solar project GEN-2022-168, Henry County is a 380 MW solar request withdrawn in the SPP interconnection queue, in Henry County, Missouri, connecting to KCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-168
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
Silwell - Clinton 161 kV Line
Location
Henry County, Missouri
Technology
Solar: 380 MW
Total requested
380 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
26 February 2023
Proposed online date
December 2027
Withdrawn
March 2025

Location

Marker shows the centre of Henry County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Henry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem