United States โบ Grid โบ Interconnection queues โบ Maine
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Maine
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Pumped Storage Project Battery storage |
1,000 MW | Withdrawn / abandoned |
| Wind Onshore wind |
905 MW | Withdrawn / abandoned |
| Wind Onshore wind |
630 MW | Withdrawn / abandoned |
| Wind Onshore wind |
601 MW | Withdrawn / abandoned |
| Wind Onshore wind |
601 MW | Withdrawn / abandoned |
| Wind Onshore wind |
601 MW | Withdrawn / abandoned |
| Wind Onshore wind |
601 MW | Withdrawn / abandoned |
| Wind Onshore wind |
500 MW | Withdrawn / abandoned |
| Wind Onshore wind |
500 MW | Withdrawn / abandoned |
| Wind Onshore wind |
376 MW | Withdrawn / abandoned |
| Solar Solar |
319 MW | Withdrawn / abandoned |
| Solar Solar |
300 MW | Withdrawn / abandoned |
| Battery storage addition (see Q663) Wind + storage |
266 MW | Withdrawn / abandoned |
| Wind Project-Phase 4( MPS Queue # 8) Onshore wind |
250 MW | Withdrawn / abandoned |
| Wind Onshore wind |
250 MW | Withdrawn / abandoned |
| Number Nine Wind Farm Onshore wind |
250 MW | Withdrawn / abandoned |
| Wind Onshore wind |
246 MW | Withdrawn / abandoned |
| Wind Onshore wind |
245 MW | Withdrawn / abandoned |
| Wind Onshore wind |
241 MW | Withdrawn / abandoned |
| Wind Onshore wind |
241 MW | Withdrawn / abandoned |
| battery storage additional (see Q664) Wind + storage |
239 MW | Withdrawn / abandoned |
| Solar Solar |
218 MW | Withdrawn / abandoned |
| Wind Onshore wind |
217 MW | Withdrawn / abandoned |
| Wind Onshore wind |
216 MW | Withdrawn / abandoned |
| Wind Onshore wind |
216 MW | Withdrawn / abandoned |
| Wind Onshore wind |
214 MW | Withdrawn / abandoned |
| Wind Onshore wind |
214 MW | Withdrawn / abandoned |
| Solar plus Battery Solar + storage |
205 MW | Withdrawn / abandoned |
| Wind Onshore wind |
202 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
200 MW | Withdrawn / abandoned |
| Wind Onshore wind |
198 MW | Withdrawn / abandoned |
| Wind Onshore wind |
197 MW | Withdrawn / abandoned |
| Wind Onshore wind |
197 MW | Withdrawn / abandoned |
| Solar Solar |
165 MW | Withdrawn / abandoned |
| Solar Solar |
152 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Wind Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Wind Alternative (see 272) Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Wind Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar and Battery Solar + storage |
139 MW | Withdrawn / abandoned |
| Solar plus Battery Solar + storage |
129 MW | Withdrawn / abandoned |
| Solar Solar |
120 MW | Withdrawn / abandoned |
| Wind Onshore wind |
117 MW | Withdrawn / abandoned |
| Wind Onshore wind |
113 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
112 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
112 MW | Withdrawn / abandoned |
| Wind Onshore wind |
104 MW | Withdrawn / abandoned |
| wind Onshore wind |
104 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)