🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Maine

SOLAR + STORAGE · ISO-NE

Solar plus Battery

Solar plus Battery is a 205 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Aroostook County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1295
Grid region
ISO-NE (New England)
Connection point (POI)
Orrington-Albion Rd 345kV line (3023) near the town of Pittsfield (approximately 19 miles from Albion Rd Substation)
Location
Aroostook County, Maine
Technology
Solar: 205 MW · Battery
Total requested
205 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
9 August 2022
Proposed online date
November 2025
Withdrawn
August 2024

Location

Marker shows the centre of Aroostook County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Aroostook County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem