ONSHORE WIND Β· ISO-NE

Wind

Wind is a 630 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Aroostook County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2017 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
672
Grid region
ISO-NE (New England)
Connection point (POI)
NSTAR 345 kV K Street substation.
Location
Aroostook County, Maine
Technology
Wind: 630 MW
Total requested
630 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
26 July 2017
Proposed online date
December 2022
Withdrawn
October 2019

Location

Marker shows the centre of Aroostook County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Aroostook County