United States › Grid › Interconnection queues › Maine

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 112 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Penobscot County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedAug 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1014
Grid region
ISO-NE (New England)
Connection point (POI)
EMERA Keene Rd 115 kV substation
Location
Penobscot County, Maine
Technology
Battery: 112 MW
Total requested
112 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
22 April 2020
Proposed online date
June 2024
Withdrawn
August 2023

Location

Marker shows the centre of Penobscot County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Penobscot County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem