Queue requests in study in Kansas

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9323.4 GW
Active in queue32.6 GW140 requests
Agreement signed9,162 MW47 requests
Withdrawn38780.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

93 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-129, Labette County
Gas
910 MWIn study Labette, KSSPP Mar 2025target 2030
Gas project GEN-2024-249, Pottawatomie County
Gas
721 MWIn study Pottawatomie, KSSPP Mar 2025target 2032
Gas project ERAS-2025-008, Sumner County
Gas
721 MWIn study Sumner, KSSPP Sep 2025target 2029
Gas project ERAS-2025-006, Reno County
Gas
718 MWIn study Reno, KSSPP Sep 2025target 2030
Gas project ERAS-2025-017, Finney County
Gas
600 MWIn study Finney, KSSPP Sep 2025target 2029
Solar project GEN-2021-030, Linn County
Solar
510 MWIn study Linn, KSSPP May 2021target 2026
Onshore wind project GEN-2021-070, Hodgeman County
Onshore wind
504 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Solar project GEN-2021-096, Coffey County
Solar
500 MWIn study Coffey, KSSPP Apr 2021target 2027
Onshore wind project GEN-2024-102, Finney County
Onshore wind
401 MWIn study Finney, KSSPP Mar 2025target 2031
Solar project GEN-2024-125, Elk County
Solar
400 MWIn study Elk, KSSPP Mar 2025target 2028
Solar project GEN-2024-136, Scott County
Solar
400 MWIn study Scott, KSSPP Mar 2025target 2029
Solar + storage project ERAS-2025-015, Finney County
Solar + storage
400 MWIn study Finney, KSSPP Sep 2025target 2029
Solar project GEN-2024-067, Cloud County
Solar
380 MWIn study Cloud, KSSPP Oct 2024target 2029
Onshore wind project GEN-2022-161, Butler County
Onshore wind
360 MWIn study Butler, KSSPP Feb 2023target 2029
Solar project GEN-2023-015, Finney County
Solar
330 MWIn study Finney, KSSPP Oct 2023target 2026
Onshore wind project GEN-2024-258, Allen County
Onshore wind
300 MWIn study Allen, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-137, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Solar + storage project GEN-2024-215, Cloud County
Solar + storage
300 MWIn study Cloud, KSSPP Mar 2025target 2029
Solar project GEN-2023-099, Jackson County
Solar
300 MWIn study Jackson, KSSPP Oct 2023target 2030
Solar project GEN-2022-013, Bourbon County
Solar
300 MWIn study Bourbon, KSSPP Jun 2022target 2028
Onshore wind project GEN-2024-138, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-142, Mcpherson County
Onshore wind
300 MWIn study Mcpherson, KSSPP Mar 2025target 2031
Gas project GEN-2024-253, Leavenworth County
Gas
300 MWIn study Leavenworth, KSSPP Mar 2025target 2027
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Onshore wind project GEN-2024-016, Smith County
Onshore wind
300 MWIn study Smith, KSSPP Oct 2024target 2028
Onshore wind project GEN-2023-107, Finney County
Onshore wind
300 MWIn study Finney, KSSPP Oct 2023target 2030
Battery storage project GEN-2025-SR16, Sumner County
Battery storage
300 MWIn study Sumner, KSSPP Jun 2025target 2026
Onshore wind project GEN-2024-144, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Battery storage project GEN-2021-006, Labette County
Battery storage
300 MWIn study Labette, KSSPP May 2021target 2026
Solar + storage project GEN-2024-166, Sedgwick County
Solar + storage
275 MWIn study Sedgwick, KSSPP Mar 2025target 2030
Solar project GEN-2022-015, Decatur County
Solar
270 MWIn study Decatur, KSSPP Jun 2022target 2028
Battery storage project GEN-2021-029, Linn County
Battery storage
254 MWIn study Linn, KSSPP May 2021target 2026
Solar project GEN-2023-220, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar project GEN-2023-221, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar project GEN-2024-032, Stevens County
Solar
250 MWIn study Stevens, KSSPP Oct 2024target 2028
Solar project GEN-2024-139, Coffey County
Solar
250 MWIn study Coffey, KSSPP Mar 2025target 2033
Battery storage project GEN-2024-176, Reno County
Battery storage
250 MWIn study Reno, KSSPP Mar 2025target 2028
Onshore wind project GEN-2021-069, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2024-193, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2024-194, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2021-068, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Solar project GEN-2022-214, Sumner County
Solar
239 MWIn study Sumner, KSSPP Mar 2023target 2028
Solar + storage project GEN-2024-069, Crawford County
Solar + storage
228 MWIn study Crawford, KSSPP Oct 2024target 2028
Battery storage project GEN-2024-330, Butler County
Battery storage
225 MWIn study Butler, KSSPP Mar 2025target 2028
Solar project GEN-2024-257, Pratt County
Solar
220 MWIn study Pratt, KSSPP Mar 2025target 2029
Battery storage project GEN-2020-090, Bourbon County
Battery storage
204 MWIn study Bourbon, KSSPP Apr 2020target 2026
Solar project GEN-2021-107, Pottawatomie County
Solar
202 MWIn study Pottawatomie, KSSPP May 2021target 2026
Battery storage project GEN-2023-037, Wyandotte County
Battery storage
200 MWIn study Wyandotte, KSSPP Oct 2023target 2028
Solar project GEN-2024-228, Rice County
Solar
200 MWIn study Rice, KSSPP Mar 2025target 2030
Battery storage project GEN-2024-061, Cowley County
Battery storage
200 MWIn study Cowley, KSSPP Oct 2024target 2028
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)