United States › Grid › Interconnection queues › Kansas

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-069, Crawford County

Solar + storage project GEN-2024-069, Crawford County is a 228 MW solar + storage request in interconnection study in the SPP interconnection queue, in Crawford County, Kansas, connecting to WERE.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-069
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Franklin 69 kV Substation
Location
Crawford County, Kansas
Technology
Solar: 228 MW · Battery
Total requested
228 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
30 October 2024
Proposed online date
December 2028

Location

Marker shows the centre of Crawford County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Crawford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem