WIND + STORAGE Β· SPPWind + storage project GEN-2023-231, Crawford County
Wind + storage project GEN-2023-231, Crawford County is a 310 MW wind + storage request withdrawn in the SPP interconnection queue, in Crawford County, Kansas, connecting to Evergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-231
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- Evergy
- Connection point (POI)
- Neosho - LaCynge 345 kV Line
- Location
- Crawford County, Kansas
- Technology
- Wind: 310 MW Β· Battery
- Total requested
- 310 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2028
- Withdrawn
- August 2025
Location
Marker shows the centre of Crawford County; the queue data does not give exact sites.
Other requests in Crawford County
- Solar + storage project GEN-2024-069, Crawford CountySolar + storage Β· 228 MW Β· in study
- Solar project GEN-2024-287, Crawford CountySolar Β· 200 MW Β· in study
- Gas project GEN-2012-044, Crawford CountyGas Β· 2.0 MW Β· built
- Gas project GEN-2003-012, Crawford CountyGas Β· 350 MW Β· withdrawn
- Battery storage project GEN-2023-025, Crawford CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project GEN-2017-050, Crawford CountySolar Β· 25.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem