United States › Grid › Interconnection queues › Kansas
BATTERY STORAGE · SPPBattery storage project GEN-2023-037, Wyandotte County
Battery storage project GEN-2023-037, Wyandotte County is a 200 MW battery storage request in interconnection study in the SPP interconnection queue, in Wyandotte County, Kansas, connecting to KACY.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2023-037
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- KACY
- Connection point (POI)
- Nearman 161 kV Substation
- Location
- Wyandotte County, Kansas
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 2 October 2023
- Proposed online date
- July 2028
Location
Marker shows the centre of Wyandotte County; the queue data does not give exact sites.
Other requests in Wyandotte County
- Battery storage project GEN-2024-320, Wyandotte CountyBattery storage · 199 MW · in study
- Battery storage project GEN-2024-319, Wyandotte CountyBattery storage · 199 MW · in study
- Battery storage project ERAS-2025-029, Wyandotte CountyBattery storage · 170 MW · in study
- Other project ERAS-2025-031, Wyandotte CountyOther · 150 MW · in study
- Battery storage project GEN-2023-023, Wyandotte CountyBattery storage · 200 MW · withdrawn
- Solar project GEN-2018-062, Wyandotte CountySolar · 75.6 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem