Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6511.4 GW
Active in queue4,195 MW17 requests
Agreement signed3,820 MW15 requests
Withdrawn6511.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

65 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Other project Q57, San Bernardino County
Other
850 MWWithdrawn / abandoned San Bernardino, CAWest Jan 2017target 2020
Mesaville Solar
Solar + storage
706 MWWithdrawn / abandoned Riverside, CACAISO May 2017target 2022
Solar project 2017-G1
Solar
600 MWWithdrawn / abandoned CAWest Jan 2017target 2024
Panoche Energy Center
Gas
432 MWWithdrawn / abandoned Fresno, CACAISO Dec 2017target 2018
Westside Canal Energy Center
Solar + storage
425 MWWithdrawn / abandoned Imperial, CACAISO May 2017target 2021
Creosote
Solar
419 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2021
Golden Square
Solar + storage
410 MWWithdrawn / abandoned Fresno, CACAISO May 2017target 2021
Canella 2 Solar Farm
Solar + storage
400 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2020
Sourgrass Solar
Solar
380 MWWithdrawn / abandoned Tehama, CACAISO May 2017target 2020
Ventura Energy Center
Gas
326 MWWithdrawn / abandoned Ventura, CACAISO May 2017target 2020
Wardenclyffe
Battery storage
314 MWWithdrawn / abandoned Alameda, CACAISO May 2017target 2022
Hidden Hills Solar 1
Solar
306 MWWithdrawn / abandoned Inyo, CACAISO May 2017target 2021
Vision Wind
Onshore wind
281 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2023
Longspur 10
Solar
264 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2021
Dasos 10
Solar
210 MWWithdrawn / abandoned Merced, CACAISO May 2017target 2020
Perseus Solar
Solar
209 MWWithdrawn / abandoned Merced, CACAISO May 2017target 2021
Romero Creek Solar
Solar
204 MWWithdrawn / abandoned Merced, CACAISO May 2017target 2022
Vermillion Energy Storage
Battery storage
204 MWWithdrawn / abandoned Riverside, CACAISO May 2017target 2023
Vanguard Solar BESS
Solar + storage
200 MWWithdrawn / abandoned Fresno, CACAISO May 2017target 2025
Lotus 2 Solar Farm
Solar + storage
200 MWWithdrawn / abandoned Madera, CACAISO May 2017target 2020
Goldwick Solar Farm
Solar + storage
200 MWWithdrawn / abandoned Stanislaus, CACAISO May 2017target 2020
Calhawk Solar Farm
Solar + storage
200 MWWithdrawn / abandoned Tulare, CACAISO May 2017target 2022
Munz Solar 1
Solar + storage
180 MWWithdrawn / abandoned Los Angeles, CACAISO May 2017target 2020
Wistaria Solar 2
Solar
156 MWWithdrawn / abandoned Imperial, CACAISO May 2017target 2019
American Kings 10
Solar
156 MWWithdrawn / abandoned Fresno, CACAISO May 2017target 2021
West Springs 2 Wind Farm
Onshore wind
155 MWWithdrawn / abandoned Riverside, CACAISO May 2017target 2023
Quartzite 10
Solar
155 MWWithdrawn / abandoned Riverside, CACAISO May 2017target 2023
East-Bay-Wind
Onshore wind
153 MWWithdrawn / abandoned Alameda, CACAISO May 2017target 2023
King Flat Wind Farm 1
Onshore wind
152 MWWithdrawn / abandoned Yolo, CACAISO May 2017target 2020
Firehawk Solar 1
Solar + storage
150 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2020
Exchequer
Hydro
112 MWWithdrawn / abandoned Mariposa, CACAISO May 2017target 2019
Blue Mountain Wind
Onshore wind
108 MWWithdrawn / abandoned Los Angeles, CACAISO May 2017target 2020
Puerta Renewable Energy Reliability Center
Solar + storage
105 MWWithdrawn / abandoned Fresno, CACAISO May 2017target 2019
Sage Solar
Solar
103 MWWithdrawn / abandoned Alameda, CACAISO May 2017target 2020
Las Camas 2
Solar
103 MWWithdrawn / abandoned Merced, CACAISO May 2017target 2021
Kerrness Solar
Solar
102 MWWithdrawn / abandoned Merced, CACAISO May 2017target 2021
Rubita
Solar
102 MWWithdrawn / abandoned San Bernardino, CACAISO May 2017target 2023
Oakland Energy Reliability Center
Battery storage
102 MWWithdrawn / abandoned Alameda, CACAISO May 2017target 2019
King Flat Wind Farm 2
Onshore wind
102 MWWithdrawn / abandoned Yolo, CACAISO May 2017target 2020
Gabriel Solar 3
Solar
100 MWWithdrawn / abandoned San Bernardino, CACAISO May 2017target 2019
Chanson Energy Storage Facility
Battery storage
100 MWWithdrawn / abandoned Calaveras, CACAISO May 2017target 2020
Solar + storage project 2017-G2, Contra Costa County
Solar + storage
100 MWWithdrawn / abandoned Contra Costa, CAWest Sep 2017target 2021
Kroe Hybrid
Solar + storage
100 MWWithdrawn / abandoned Merced, CACAISO May 2017target 2019
Wilbur Energy Storage
Battery storage
94.5 MWWithdrawn / abandoned Contra Costa, CACAISO May 2017target 2023
Mallard Energy Storage Project
Battery storage
90.0 MWWithdrawn / abandoned Contra Costa, CACAISO May 2017target 2021
Vickers Energy Storage
Battery storage
80.0 MWWithdrawn / abandoned Los Angeles, CACAISO May 2017target 2021
Solar project Q59, Kern County
Solar
77.0 MWWithdrawn / abandoned Kern, CAWest Mar 2017target 2020
Cassiopeia Solar
Solar
77.0 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2021
Curry Solar
Solar
71.5 MWWithdrawn / abandoned Fresno, CACAISO May 2017target 2020
Battery storage project Q60, Kern County
Battery storage
65.0 MWWithdrawn / abandoned Kern, CAWest Jun 2017target 2019
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)