United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESQueue requests in study in PJM (Mid-Atlantic, Midwest) (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Maidsville CCGT Gas |
1,270 MW | Paused / redesign |
| Ocean Wind Offshore wind |
816 MW | Paused / redesign |
| Ocean Wind LLC Offshore wind |
432 MW | Paused / redesign |
| Livingston Wind Onshore wind Β· Livingston Wind Project, LLC |
255 MW | In study |
| Broomstick Solar Energy Centergy Center Solar |
210 MW | Paused / redesign |
| Fountain Point Solar Solar Β· Fountain Point Solar Energy LLC |
207 MW | In study |
| Lower Crossing Wind Onshore wind |
200 MW | Paused / redesign |
| Golden Aster Solar Energy Center Solar |
160 MW | Paused / redesign |
| Energy Mountain Battery storage |
150 MW | Paused / redesign |
| Wingstem Solar Energy Farm Solar |
150 MW | Paused / redesign |
| Leaf River Wind Onshore wind Β· Leaf River Wind, LLC |
150 MW | In study |
| Pilesgrove Solar Project Solar |
149 MW | Paused / redesign |
| Maroon Solar Solar |
149 MW | Paused / redesign |
| Meadow Forge Solar Energy Center Solar |
130 MW | Paused / redesign |
| CC Solar I Solar |
120 MW | Paused / redesign |
| Strawhat Solar Energy Center Solar |
110 MW | Paused / redesign |
| Headwaters Wind Farm III Onshore wind |
100 MW | Paused / redesign |
| Madison County Solar Solar |
100 MW | Paused / redesign |
| Blue Jay Solar Solar |
100 MW | Paused / redesign |
| Headwaters Wind Farm III Onshore wind |
100 MW | Paused / redesign |
| Bakers Pond Solar Solar |
100 MW | Paused / redesign |
| Brandonville Solar Solar |
99.6 MW | Paused / redesign |
| Raleigh Solar Project Solar |
90.0 MW | Paused / redesign |
| Beaver Creek Solar Solar |
80.3 MW | Paused / redesign |
| Strinestown Solar Project Solar |
79.6 MW | Paused / redesign |
| Broomstick Solar Energy Centergy Center Solar |
50.0 MW | Paused / redesign |
| Hardin Energy Center βΓΓ¬ Storage I Battery storage |
50.0 MW | Paused / redesign |
| Cadence Energy Storage Battery storage |
50.0 MW | Paused / redesign |
| Recreation Solar Solar |
49.5 MW | Paused / redesign |
| Concho Solar I Solar |
49.0 MW | Paused / redesign |
| Vinton Energy Storage Battery storage |
42.0 MW | Paused / redesign |
| Ho-Fel Solar Solar |
40.0 MW | Paused / redesign |
| Blue Creek Wind Farm Solar |
26.0 MW | Paused / redesign |
| Confer Solar I Solar |
20.0 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)40 Β· 10.2 GW
- PJM (Mid-Atlantic, Midwest)34 Β· 5,884 MW
- NYISO (New York)15 Β· 3,444 MW
- ERCOT (Texas)16 Β· 2,703 MW
- Southeast (non-ISO utilities)13 Β· 1,590 MW
- CAISO (California)4 Β· 1,302 MW
- ISO-NE (New England)1 Β· 827 MW
- SPP (Southwest Power Pool)3 Β· 500 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)