United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6222.5 GW
Active in queue120.8 GW390 requests
Agreement signed180 MW1 requests
Withdrawn6222.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

62 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project APP-100096
Gas
1,640 MWWithdrawn / abandoned LAMISO Aug 2025
Gas project APP-100103
Gas
1,640 MWWithdrawn / abandoned LAMISO Aug 2025
Gas project J4022, Ouachita Parish County
Gas
1,509 MWWithdrawn / abandoned Ouachita Parish, LAMISO May 2025target 2030
Gas project J4109, Iberville Parish County
Gas
1,300 MWWithdrawn / abandoned Iberville Parish, LAMISO Oct 2025target 2030
Gas project E0025, Linn County
Gas Β· Interstate Power and Light Company (IPL)
987 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Gas project APP-100016
Gas
770 MWWithdrawn / abandoned LAMISO Aug 2025
Gas project J4166, Iberville Parish County
Gas
710 MWWithdrawn / abandoned Iberville Parish, LAMISO Sep 2025target 2029
Linn County Generating Facility
Nuclear Β· NextEra Energy Resources Development, LLC
676 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Gas project J4141, Morehouse Parish County
Gas
650 MWWithdrawn / abandoned Morehouse Parish, LAMISO Oct 2025target 2030
Gas project J4111, Hot Spring County
Gas
650 MWWithdrawn / abandoned Hot Spring, ARMISO Oct 2025target 2030
Solar project J3937, Dallas County
Solar
500 MWWithdrawn / abandoned Dallas, ARMISO Apr 2025target 2030
Gas project J4020, Kenosha County
Gas
481 MWWithdrawn / abandoned Kenosha, WIMISO May 2025target 2030
Solar project J3998, Cerro Gordo County
Solar
450 MWWithdrawn / abandoned Cerro Gordo, IAMISO Feb 2025target 2030
Onshore wind project J4135, Grant County
Onshore wind
450 MWWithdrawn / abandoned Grant, SDMISO Oct 2025target 2030
Gas project J4032, Deuel County
Gas
442 MWWithdrawn / abandoned Deuel, SDMISO May 2025target 2030
Solar project J3965, Christian County
Solar
402 MWWithdrawn / abandoned Christian, ILMISO Apr 2025target 2030
Solar project J3952, Polk County
Solar
395 MWWithdrawn / abandoned Polk, MNMISO Feb 2025target 2030
Solar project J4004, Peoria County
Solar
392 MWWithdrawn / abandoned Peoria, ILMISO May 2025target 2032
Surplus; J1058
Solar
365 MWWithdrawn / abandoned Itasca, MNMISO May 2025target 2027
Battery storage project J4171, Racine County
Battery storage
300 MWWithdrawn / abandoned Racine, WIMISO Oct 2025target 2029
Battery storage project J4162, Stearns County
Battery storage
300 MWWithdrawn / abandoned Stearns, MNMISO Sep 2025target 2028
Solar project J3958, Sullivan County
Solar
300 MWWithdrawn / abandoned Sullivan, MOMISO Apr 2025target 2029
Onshore wind project J3920, Clay County
Onshore wind
300 MWWithdrawn / abandoned Clay, IAMISO Mar 2025target 2030
Onshore wind project J3995, Jasper County
Onshore wind
300 MWWithdrawn / abandoned Jasper, ILMISO Apr 2025target 2030
Battery storage project J4104, Houston County
Battery storage
250 MWWithdrawn / abandoned Houston, TXMISO Oct 2025target 2030
Onshore wind project J4027, Clay County
Onshore wind
250 MWWithdrawn / abandoned Clay, ARMISO May 2025target 2030
Battery storage project J4136, Grant County
Battery storage
250 MWWithdrawn / abandoned Grant, SDMISO Oct 2025target 2030
Solar project J3934, Mcleod County
Solar
250 MWWithdrawn / abandoned Mcleod, MNMISO Feb 2025target 2029
Onshore wind project J3956, Wilkin County
Onshore wind
240 MWWithdrawn / abandoned Wilkin, MNMISO Apr 2025target 2030
Solar project J3951, Polk County
Solar
218 MWWithdrawn / abandoned Polk, MNMISO Feb 2025target 2030
Solar project J3893, Phillips County
Solar
214 MWWithdrawn / abandoned Phillips, ARMISO Feb 2025target 2030
Onshore wind project APP-100087
Onshore wind
203 MWWithdrawn / abandoned NDMISO Aug 2025
Battery storage project J4192, Racine County
Battery storage
200 MWWithdrawn / abandoned Racine, WIMISO Oct 2025target 2029
Solar project J3885, Morehouse Parish County
Solar
200 MWWithdrawn / abandoned Morehouse Parish, LAMISO Feb 2025target 2030
Onshore wind project J4064, Tallahatchie County
Onshore wind
200 MWWithdrawn / abandoned Tallahatchie, MSMISO Sep 2025target 2030
Onshore wind project J3972, Liberty County
Onshore wind
200 MWWithdrawn / abandoned Liberty, TXMISO Mar 2025target 2029
Battery storage project J3989, Williamson County
Battery storage
200 MWWithdrawn / abandoned Williamson, ILMISO Apr 2025target 2030
Solar project J3933, Franklin County
Solar
200 MWWithdrawn / abandoned Franklin, IAMISO Feb 2025target 2028
Solar project J4197, Drew County
Solar
200 MWWithdrawn / abandoned Drew, ARMISO Sep 2025target 2030
Solar project J3997, Pike County
Solar
200 MWWithdrawn / abandoned Pike, INMISO May 2025target 2028
Solar project J3826, Holmes County
Solar
198 MWWithdrawn / abandoned Holmes, MSMISO Oct 2025target 2026
Solar project J3969, Poinsett County
Solar
196 MWWithdrawn / abandoned Poinsett, ARMISO Mar 2025target 2030
Battery storage project J4067, Panola County
Battery storage
180 MWWithdrawn / abandoned Panola, MSMISO Sep 2025target 2029
Solar project J4036, Cross County
Solar
160 MWWithdrawn / abandoned Cross, ARMISO Jul 2025target 2029
Solar project J3877, Pike County
Solar
160 MWWithdrawn / abandoned Pike, INMISO Jan 2025target 2029
Solar project J4033, Christian County
Solar
157 MWWithdrawn / abandoned Christian, ILMISO Jun 2025target 2030
Battery storage project J4108, Webster Parish County
Battery storage
150 MWWithdrawn / abandoned Webster Parish, LAMISO Oct 2025target 2030
Battery storage project J4107, Covington County
Battery storage
150 MWWithdrawn / abandoned Covington, MSMISO Oct 2025target 2030
Solar project J3912, Chippewa County
Solar
150 MWWithdrawn / abandoned Chippewa, WIMISO Feb 2025target 2030
Onshore wind project J4149, Grant County
Onshore wind
150 MWWithdrawn / abandoned Grant, SDMISO Oct 2025target 2030
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)