United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project J3956, Wilkin County

Onshore wind project J3956, Wilkin County is a 240 MW onshore wind request withdrawn in the MISO interconnection queue, in Wilkin County, Minnesota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3956
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Hankinson 230 kV Substation
Location
Wilkin County, Minnesota
Technology
Wind: 240 MW
Total requested
240 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
21 April 2025
Proposed online date
June 2030
Withdrawn
December 2025

Location

Marker shows the centre of Wilkin County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Wilkin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem