United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project J035, Wilkin County
Onshore wind project J035, Wilkin County is a 4.9 MW onshore wind request withdrawn in the MISO interconnection queue, in Wilkin County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2009 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedDec 2010 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J035
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- OTP Wahpeton 41.6 kV
- Location
- Wilkin County, Minnesota
- Technology
- Wind: 4.9 MW
- Total requested
- 4.9 MW
- Study phase
- DPP - SIS
- Queue status
- Withdrawn
- Entered queue
- 16 March 2009
- Agreement signed
- 28 December 2010
- Proposed online date
- November 2010
Location
Marker shows the centre of Wilkin County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Wilkin County
- Battery storage project J2492, Wilkin CountyBattery storage Β· 300 MW Β· withdrawn
- Onshore wind project J3956, Wilkin CountyOnshore wind Β· 240 MW Β· withdrawn
- Onshore wind project G913, Wilkin CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project GI-0719, Wilkin CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project H031, Wilkin CountyOnshore wind Β· 160 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem