United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
SOLAR Β· MISOSolar project J3969, Poinsett County
Solar project J3969, Poinsett County is a 196 MW solar request withdrawn in the MISO interconnection queue, in Poinsett County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedJan 2026 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3969
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- HARRISBURG
- Location
- Poinsett County, Arkansas
- Technology
- Solar: 196 MW
- Total requested
- 196 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 10 March 2025
- Proposed online date
- October 2030
- Withdrawn
- January 2026
Location
Marker shows the centre of Poinsett County; the queue data does not give exact sites.
Other requests in Poinsett County
- Battery storage project J4174, Poinsett CountyBattery storage Β· 140 MW Β· in study
- Solar + storage project J2773, Poinsett CountySolar + storage Β· 100 MW Β· in study
- Solar project J3569, Poinsett CountySolar Β· 300 MW Β· withdrawn
- Solar project J2386, Poinsett CountySolar Β· 300 MW Β· withdrawn
- Solar project J3571, Poinsett CountySolar Β· 250 MW Β· withdrawn
- Solar project J3373, Poinsett CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project J3536, Poinsett CountySolar + storage Β· 190 MW Β· withdrawn
- Solar project J2928, Poinsett CountySolar Β· 160 MW Β· withdrawn
- Solar project J948, Poinsett CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J2521, Poinsett CountyBattery storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem