United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J3969, Poinsett County

Solar project J3969, Poinsett County is a 196 MW solar request withdrawn in the MISO interconnection queue, in Poinsett County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedJan 2026 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3969
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
HARRISBURG
Location
Poinsett County, Arkansas
Technology
Solar: 196 MW
Total requested
196 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
10 March 2025
Proposed online date
October 2030
Withdrawn
January 2026

Location

Marker shows the centre of Poinsett County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Poinsett County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem