Solar project J2928, Poinsett County

Solar project J2928, Poinsett County is a 160 MW solar request withdrawn in the MISO interconnection queue, in Poinsett County, Arkansas, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2928
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Harrisburg 161 kV Substation
Location
Poinsett County, Arkansas
Technology
Solar: 160 MW
Total requested
160 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
2 September 2022
Proposed online date
September 2026
Withdrawn
March 2023

Location

Marker shows the centre of Poinsett County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Poinsett County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem